Question #56Quantitative AptitudeHard

A can finish a job in 12 days and B can finish the same job in 18 days. If they work together at their usual rates, how many days will they take to finish the job?

  1. A6 days
  2. B7 15\dfrac{1}{5} days
  3. C8 days
  4. D9 days
Show answer & explanation

Correct answer: B.

Add the workers’ daily work rates, then take the reciprocal.

1
Add daily work rates
A completes of the job per day; B completes .
Together: + = of the job per day.
2
Find the time
Time = 1 ÷ () = days = 7 days.
Final Answer
7 days